Construction of biomass boiler plants (UNDP )

Construction of biomass boiler plants in of the project was financed by the European Union and coordinated by UNDP ” Energy and Biomass „
  • Implementation period was December 2011 – current .
  • The estimated value of contracts is 3 450 000.00 $
The project included the design, construction and commissioning of biomass heating plants in different regions of the country . In total was 39 boiler plants were built that were installed 61 boilers with output ranging between 41 and 340 kW. In addition, for hot water were installed 50 solar collectors Apricus evacuated tube with 30 each. Summary thermal power at boilers plants built it exceeds 9.8 MW. The works included the renovation of the room boilers in some cases, and in other building construction , automation works , electrical works , water and sanitation , according to the latest energy efficiency technologies and use of more efficient equipment. Period of the implementation:
  • December 2011 – June 2012 – The construction of biomass boiler plants in villages Alexandreni , Bilicenii Noi, Bursuceni , Pepeni and Dumbravita of the Singerei district, with the installation of three boilers Thermostahl MCL BIO 80, 1 boiler MCL BIO 40, 1 boiler MCL BIO 36, 1 boiler MCL BIO 180, one boiler MCL BIO 160 and boiler AKU 34 kW.
 
  • June 2012 – December 2012 – The construction of biomass boilers plants in villages Camencea, Cuhnesti, Fundurii Vechi, Petrunea and Ustia from Glodeni district with the installation of three boilers Thermostahl MCL 200, two boilers MCL 150, two boilers MCL 120, 1 boiler MCL 60, one boiler MCL 40 and 1 boiler MCL 42.
 
  • September 2012 – April 2013 – The construction of biomass boiler plants in villages Biesti, Camencea, Mitoc and Morozeni from Orhei district with instalation of one boiler MCL 300, one boiler MCL 250, one boiler MCL 100  and one boiler MCL 80.
 
  • October 2013 – May 2014 – The construction of biomass boiler plants in villages Saseni and Hirbovat in Calarasi district, Bratuleni and Soldanesti in Nisporeni district, Micleuseni and Vorniceni of Straseni district, with the installation of three boilers Galmet Expert 60M , 6 boilers D’ Alessandro CSA Termimecanica Marina 130 and one boiler Marina D’ Alessandro Termimecanica CSA 230 .
 
  • June 2014 – December 2014 – The construction of biomass boiler plants in villages Cotiujeni and Grimancauti in Briceni district, Hadarauti of Ocnita district, Ruseni and Parcova in the Edinet district and Nicoreni in Drochia district, with the installation of three boilers SAS AGRO ECO 125 ​​kW, two boilers SAS AGRO ECO 125 ​​kW, two boilers SAS AGRO ECO 90 kW , one boiler SAS AGRO ECO 78 kW and one boiler SAS AGRO ECO 48 kW.
 
  • November 2015 – July 2016 – Construction of the biomass boiler plants in the city  Leova , Cimislia and Causeni, villages Baurci and Copceag of UTAG, Congaz, Cazaclia of Taraclia district, in city Taraclia, villages Corten, Albota de Jos, Sofievca and Ciumai in Taraclia district with installation 9 Boiler SAS AGRO ECO 100 kW, two boilers SAS AGRO ECO 90 kW, two boilers SAS AGRO ECO 150 kW, two boilers SAS ECO 175 kW and 4 boilers SAS ECO 250 kW. For hot water were installed 50 solar collectors Apricus with 30 vacuum tubes each.